The difficulty of the project was that we had to keep the existing and running pump station of the factory intact and built the new pump station around the old one. And only then did we remove the walls of the existing small station and made it into one bigger building. We had to overcome the obstacle of so many engineering communication lines resulting so many delays but eventually managed to complete the project within given time schedule.